Regulations

11.0656 Prohibition Against Gratuities and Kickbacks.

A. It shall be a breach of ethical standards…

11.0657 Prohibition Against Contingent Fees.

A. It shall be a breach of ethical standards…

11.0658 Restrictions On Employment.

A. Present employees. It shall be a breach of…

11.0659 One Year Representation Restriction Regarding Matters For Which A Former Employee Was Officially Responsible.

It shall be a breach of ethical standards for…

11.0660 Disqualification Of Business When An Employee Has A Financial Interest.

It shall be a breach of ethical standards for…

11.0661 Selling To LBJ Within 6 Months After Termination Of Employment Is Prohibited.

It shall be a breach of ethical standards for…

11.0662 Policy.

A. Collusion or secret agreement between bidd…

11.0663 Prohibition Against Employee Use And Contractor Acceptance Of Purchase Requisitions.

A. Only valid purchase orders and contracts a…

11.0664 Civil Penalties.

A. An employee who violates a provision of th…

12.0101 Intent.

The ASG desires that the business of generati…

12.0102 Authority.

The executive order embodied in Rule 12-81 an…

12.0103 Establishment

There is established a governmental agency wi…

12.0104 Powers.

The American Samoa power authority: (1) may m…

12.0105 Board of directors-Appointment-Meetings-Compensation.

(a) The authority is governed by a board of 5…

12.0106 Board of directors-Powers and duties.

All powers vested in the authority are exerci…

12.0107 Personnel.

All officers and employees of the authority o…

12.0108 Transfer of existing utility-Property valuation-ASG capital contributions and loans.

(a) At a date fixed by the board of directors…

12.0109 Accounting-Budget.

The authority shall assume responsibility for…

12.0110 Audit-Consultants-Annual report.

(a) The authority shall employ a firm of inde…

12.0111 Transition period.

All rates, charges, and classifications of th…

12.0201 Service generally-Utility defined-Rate review.

(a) Electric power is generated and distribut…

12.0202 Bill payment-Late penalty.

(a) Payment shall be due on the date shown on…

12.0203 Disconnection for nonpayment-Reconnection.

(a) If the bill becomes delinquent, the servi…

12.0204 Connections.

All final connections, permanent or temporary…

12.0205 Tampering with meters and conductors-Breaking seals.

(a) Tampering with the meter or with conducto…

12.0206 Alterations and additions to electrical equipment installations.

When the utility connects a customer’s instal…

12.0207 Liability limits of utility-Three-phase circuit protection.

(a) Thc utility will endeavor to furnish cont…

12.0208 Phasing failure and protection.

Delivery of single-phase power to a 3-phase m…

12.0209 Resale of energy.

The customer shall not resell any of the elec…

12.0210 Limit of utility responsibility.

The primary delivery point shall be the pole…

12.0211 Trouble calls.

The utility is responsible for maintaining el…

12.0212 Meter calibration.

On request, the utility will test a customer’…

12.0213 Public information and requests.

The public may obtain information and make re…

12.0214 Current specifications-Three-phase availability-Equipment-purchase warning.

(a) Power will normally be delivered at 120/2…

12.0215 Application for service-Notice of contemplated installations.

(a) Customers or prospective customers should…

12.0216 Easement requirement.

Consumers must execute or have the owner of t…

12.0217 Installation charges.

Installation charges for new service: Type of…

12.0218 Deposits.

(a) When, in the judgment of the utility, til…

12.0219 Power line extension fees.

There is levied a comprehensive fee to cover…

12.0220 Delivery point-Defined-Approval-Multiple occupancy.

(a) The delivery point is the point where the…

12.0221 Delivery point-Designation-Anchorage for connections.

(a) It is essential, in order to avoid errors…

12.0222 Separate conductors with single drop.

Where no accessible common meter location is…

12.0223 Meter location.

(a) For business houses normally open during…

12.0224 Number of services and meters.

The utility will connect only 1 set of servic…

12.0225 Grounding requirement.

Ground wires installed in accordance with the…

12.0226 Meter equipment issuance.

When the electrician is ready to wire the bui…

12.0227 Inspection before energization.

All wiring in all buildings must be inspected…

12.0228 Noncomplying construction.

The utility reserves the right to refuse serv…

12.0229 Temporary services.

(a) In ease temporary service is desired, the…

12.0230 Termination of service.

(a) Once service is established, the consumer…